2025 Excellence in Environmental Engineering and Science® Awards Competition Winner
Superior Achievement
Category Entered: Design
Morro Bay Water Resources Center
Entrant: Black & Veatch Engineer in Charge: Chad Brown Location: Morro Bay, California
Entrant Profile

Entrant: BLACK & VEATCH
Design-Builder: FILANC BLACK & VEATCH (JOINT VENTURE)
Project Owner: CITY OF MORRO BAY, CA
Structural Engineer: ASHLEY & VANCE ENGINEERING
Owner’s Advisor: CAROLLO ENGINEERS
Electrical/I&C Subcontractor: ELECTICRAFT INC.
Architect: FRASER SEIPLE ARCHITECTS
For the Morro Bay Water Reclamation Facility Design-Build project, the entrant, Black & Veatch, was the design-builder in a 50/50 joint venture with Filanc Construction named Filanc Black & Veatch.
 |
Aerial photo of completed Morro Bay Water Resources Center (originally Morro Bay Water Reclamation Facility).
|
 |
Facility entrance was designed to match the agricultural look of the region while hiding treatment facilities themselves from the view of surrounding community and tourists.
|
 |
A full rainbow greeted visitors during the facility’s dedication event in 2023. The city continues to give regular public tours to expand understanding and acceptance of water reuse.
|
Project Description
Comprehensive, Integrated Approach
The City of Morro Bay faced multiple challenges: the California Coastal Commission would not renew the permit for their aging 60-year-old wastewater treatment plant (WWTP) because it was located directly on the beach, in a flood zone, placing the coastal environment in jeopardy; their existing WWTP was unable to meet upcoming ocean discharge requirements; and, being dependent on imported water, they needed a new local, sustainable water supply. Overall, Morro Bay had a tight budget as this would bethe largest project the city had ever undertaken.
Filanc Black & Veatch (FBV), a joint-venture between Filanc Construction and Black & Veatch delivered a new plant via fixed-price design-build that addressed all of these challenges while producing significantly better water quality than city’s anticipated solution. The new facility treats all of Morro Bay’s wastewater, up to 8.14 million gallons per day (mgd), while producing two separate effluent streams with three different process trains. Normally, the plant’s flow istreated with biological nutrient reduction (BNR) paired with a membrane bio reactor (MBR). This produces water witha tenth of the ammonia and a less than a hundredth of the turbidity than its predecessor. This water is then treated further with reverse- osmosis (RO) followed by ultra-violet advanced oxidation process (UV-AOP), calcite buffering, and free-chlorine disinfection to produce 800,000 gallons per day of highly purified water for indirect potable reuse (IPR) via direct aquifer injection. When the plant sees peak flows exceeding 1.88 mgd, the additional flow is treated through a primary filtration process and blended with MBR effluent for ocean discharge.
Quality
FBV leveraged the design-build process to produce a highly advanced wastewater treatment plant that met discharge permit requirements from the moment it started up. Less than three months later, when the city was hit with a historic storm, the old plant was flooded under five feet of water and mud, rendering it inoperable. Meanwhile, the new plant continued operations uninterrupted while meeting all discharge requirements.
Quality started before the project was awarded, during the fixed-price proposal development. FBV used a series of design charrettes to vet design innovations and engineering alternatives.
Forty people, representing of all aspects of the design-build team, were present at the primary charette to provide input. This process compressed what would have been months of discussions into just three days. With the optimum configuration determined upfront, the team was able to focus on refining the quality of the design and itsintegration with future construction.
The plant has been in continuous operation as Morro Bay’s sole wastewater treatment plant for two years. In that time, it has reliably produced high-quality effluent, having not once violated its discharge permits. The IPR facilities at the plant have been recognized by the California Department of Drinking Water to exceed their performance requirements.
Originality & Innovation
This is the first permitted and operational mainline MBR-IPR plant in California, a technology combination that is expected to soon be replicated by many other cities. Black & Veatch engineers used a series of innovations, creative approaches, and new technology applications to make this possible within the city’s budget.
Morro Bay has an unusually high wastewater flow peaking factor. Conventionally, a large equalization basin and upsized plant would be used to handle these flows. A novel approach was developed to solve this problem for $7M less. A 1.88 mgd BNR-MBR treatment process handles normal flows. Peak flows above this are treated through a side-stream primary filtration cloth filter and blended with the MBR effluent to produce net effluent that still meets discharge requirements.
The conventional approach for hillside construction would be to flatten the site into tiers held by large retaining walls. Instead,the plant was arranged along the natural contours, so no retaining walls were needed. Over 100,000 cubic yards of soil export was averted, saving another $7M.
The plant utilizes the natural topography to propel the flow throughout the treatment processes, eliminating intermediate pumping stations, saving another $3M. For example, there are no transfer pumps between MBR and RO as would be typical. All of this was done while making the area around key facilities relatively flat and ADA accessible for public tours.
Complexity
The city had a complex problem to address. As a relatively small community, they had to undertake the largest project in their history within a tight budget. They needed to construct an entirely new WWTP away from flooding danger; it needed to meet more strict discharge requirements; and it needed to provide a new local water resource. Adding to the complexity, construction started just before March of 2020, and several cultural resources were discovered which took regulators longer to address due to the COVID-19 pandemic. As one of the first IPR plants in California, DDW also needed more time to develop their regulatory approval process. Pandemic market delays and pricing volatility were ever-present. In the middle of construction, a landslide plane was discovered. An innovative solution to bench that material into competent rock was devised. The team worked together to address these challenges while still delivering the project on budget and on-time.
Contribution to Social, Public, and Environmental Health and Economic Advancement
This new plant saved the community from an environmental and economic disaster when the old plant was destroyed in historic flooding less than three months after the new plant was started up. Had the new plant not been online, the city would have had no choice but to discharge untreated wastewater to the sensitive marine environment for months, if not years, while the old plant was being repaired.
The new plant provides a remarkable improvement in the quality of ocean discharge effluent with a tenth of the ammonia and a less than a hundredth of the turbidity than its predecessor. The high-quality IPR water produced supplements Morro Bay’s local water supply and reduces their dependence on imported water.
The new plant is the first of what will soon be many throughout California. The city has provided tours for thousands of citizens, students, and government and representatives as they prepare for their own transition to more sustainable and resilient wastewater treatment and reuse.
Click images to enlarge in separate window.
 |
 |
Image 1: The conventional approach for hillside construction would be to flatten the site into a flat tiers held by large retaining walls. Instead, our team took inspiration from the ocean surfers near Morro Rock and designed the plant to “surf” the topography of the existing hillside. This eliminated the need for retaining walls, saving the city $7M, as well as eliminating the need for intermediate pumping stations, saving another $3M. All of this was done while making the area around key facilities relatively flat and ADA accessible for public tours for no additional cost. |
Image 2: Aerial of terraced earthwork designed for the WRF site to surf the existing topography, providing balanced earthwork and using the natural site fall to drive the hydraulic flow of the plant. A buried chloramine contact pipe (large blue pipe in photo) was utilized as a cost-effective and space-saving innovation to avoid large contact tanks. |
 |
 |
Image 3: The plant was configured to work with the site’s topography and is tucked behind a hill to minimize its visual impact on the surrounding community and undeveloped countryside. The buildings were designed to look like agricultural buildings common to the area. |
Image 4: The administrative building and entrance was strategically placed to mask the wastewater treatment facilities themselves from view and appear visitor and community friendly. While simple construction materials were used, the facility matches the agricultural look of the region with a professional, modern, bright and welcoming aesthetic for the local community. The city continues to give regular public tours to community members, nearby California Polytechnic Institute University students, and representatives from cities and agencies across California to expand understanding and acceptance of indirect potable reuse (IPR) as well as the use of MBR technology at an IPR facility. |
 |
 |
Image 5: The primary filtration innovation for peak flows eliminated the need for a large equalization basin. This approach saved significant capital funds allowing the team to utilize more robust Membrane Bioreactor technology for the main plant process to achieve higher quality water being discharged to the ocean outfall or supplied to the plant’s indirect potable reuse (IPR) facilities. |
Image 6: Membrane Bioreactor (MBR) is at the heart of this facility and enables the city to produce high-quality tertiary effluent for discharge to the ocean or as supply to the indirect potable reuse (IPR) advanced treatment facilities. The city went from having a trickling filter WWTP, arguably one of the most rudimentary wastewater treatment processes, to a BNR- MBR plant with RO and UV-AOP for IPR production. |
 |
 |
Image 7: Reverse osmosis and ultra-violet advanced oxidation process (UV/AOP) are utilized to convert Membrane Bioreactor treated wastewater into high-quality indirect potable reuse water. This water will be used to supplement the city’s potable water supply via direct injection into the city’s water supply aquifer. |
Image 8: The facility’s design provides the city with flexibility to produce indirect potable reuse water and store it, pump it to injection wells, or, if needed, to send it to the ocean outfall. |
 |
 |
Image 9: Project team member performing the ultra-violet advanced oxidation process (UV/ AOP) challenge testing to demonstrate to state regulators that the facility met the stringent indirect potable reuse (IPR) regulations. |
Image 10: A full rainbow greeted visitors on a tour of the water reclamation facility during its dedication event in February 2023. Approximately 500 people from the local community toured the plant that day, learning about advanced wastewater treatment and indirect potable reuse. The city continues to give regular public tours to community members and nearby California Polytechnic Institute University to expand understanding and acceptance of indirect potable reuse. |
|